Pontoon simulation, Building BIM, Rowing race stadium tangeum lake Chungju / 충주 탄금호 조정경기장 BIM 구축 용역 중 폰툰 시뮬레이션

고객사 : Ssangyong E&C

계약기간 : 2011-08

Taesung S&I made an equipment simulation. We constructed 3d integrated construction management system based on BIM in order to examine possible construction occur rowing stadium during construction arena pontoon withdrawal when mounted and safety. It has been studying a structure construction related through the 3d information model BIM, it was pre-study workability behavior simulation equipment Engineering major species:


Review of Safety Measure. Proper Estimation of Equipment Capacity for installation.
Comparing 3D BIM with 2D based design. Quantity Estimation of the Construction materials.


Taesung S&I reviewed the construction plan with the equipment simulation and drew the proper estimation of equipment capacity.  .