BIM,T/K Construction of Center's railway (Dodam - Yeongcheon) Double Track Railway 6

고객사 : Daelim

계약기간 : 2013-09

 

Taesung S&I made a BIM based design from existing 2D based design. Then reviewed the optimum equipment capacity for installation of the elements of three Bridges and compared with 2D based design. The purposes of this project are as follows:


Proper Estimation of Equipment Capacity for installation. Review of 3D model objects and processes linkages. Review of Safety facilities. Crash Detective between Structures.

3D BIM’s information model was used to verify the construction sequence of bridges. And, proper equipment capacity and position were derived with 3D equipment simulation considering the processes linkages.