Songdo International Business District Access road Lot No. 5-7 / 송도국제도시 5-7공구 진입도로 건설공사 BIM 기법(주탑 시공 시뮬레이션)

고객사 : GS E&C

계약기간 : 2013-07

BIM’s information model of Songdo 4th Bridge in Lot No. 5-7 is made of existing 2D based drawings. Also, 3D model objects were linked with processes linkage. This construction was a high level technique to cross the road on the existing railway. So we needed to check the potential problems in advance by constructing a 3D virtual evaluation system by the method of BIM and examined the workability and the safety in the construction.

 

-  Completion of a detailed Construction Time Schedule.

-  Review of 3D model objects and processes linkages.

-  Review of Safety Measures.

-  Comparing 3D BIM with 2D based design.

 

3D BIM was used to check the safety measure considering the processes linkages and make a detailed construction time schedule.