Qatar Integrated Railway Project

고객사 : DOHAM KTQ-JV

계약기간 : 2013-05

Taesung S&I made a BIM based design from existing 2D based design. Then BIM based design compared with 2D based design. Also, traffic diversion and crash detective are reviewed using the 3D BIM. The purposes of this project are as follows:

3D Station Modeling on the structures and steelworks. Review of Traffic Diversion with Construction of Station. Estimation of Construction Materials. Comparing BIM with 2D based drawings. Review of 3D model objects and processes linkages. Crash Detective between Structures.


3D BIM was used to check the construction sequence considering the processes linkages. Also, proper traffic diversion plan was reviewed. And exact amount of materials was derived from 3D BIM.